PDLC Project Planning Guide


The table below captures some of the project planning activities that should be considered at different stages of the Product Development Life Cycle. At the moment, it concentrates heavily on the formal PMI link to product development. I will later add a list that includes additional details of engineering and release to manufacturing tasks that should be performed at each stage.

PMI

Product Development Life Cycle

PMI – Initiating

PDLC – Concept

Engineering Product Management / Sales and Marketing Manufacturing and/or Distribution
Develop Project Charter Contribute to Project Charter Contribute to Project Charter Contribute to Project Charter
Identify Stakeholders Identify Key Project Contributors and Stakeholders Perform Market Research Identify Key Project Contributors and Stakeholders

PMI – Planning

PDLC – Architecture

Engineering Product Management / Sales and Marketing Manufacturing and/or Distribution
Collect Requirements Define technical requirements, Define system architecture Define product and sales requirements Draft manufacturing strategy
Define Scope

Create WBS

Define scope (what is and is not included)

Create WBS for all tasks with clearly defined requirements

Provide clear scope to the development team High level planning of assembly and test methods
Define Activities

Sequence Activities

Define and sequence all engineering activities to develop the schedule Define and sequence all applicable activities to develop the schedule Define and sequence all release to manufacturing activities to develop the schedule
Estimate Resources

Estimate Durations

Estimate resource requirements and develop resource hiring and allocation plan Estimate resource requirements and develop resource hiring and allocation plan Estimate resource requirements and develop resource hiring and allocation plan
Develop Schedule Develop and release the schedule Ensure release timing aligns with product delivery expectations
Estimate Costs

Determine Budget

Create Preliminary BOMs

Estimate costs and develop a budget baseline

Perform updated market research and update business case Estimate Assembly, Test, Packaging and Distribution Costs
Plan Quality Define Verification Plan Define Product Quality Expectations Assembly , Test and Verification Plan
Plan Communications Develop stakeholder communications plan Develop stakeholder communications planCustomer Communications PlanningERP considerations ERP / MRP considerations
Plan Risk Management Perform Risk Assessment and take action to mitigate risks (i.e. prototyping) Perform market risk decision tree Perform Manufacturing Risk Assessment
Plan Procurements Identify long lead components Plan Contract Manufacturer, Distribution

PMI- Execution/Monitoring and Control

Execution

  Engineering Product Management / Sales and Marketing Manufacturing and/or Distribution
Direct and Manage Project Execute on development Execute on marketing and sales strategy Execute on assembly and test plan
Acquire, Develop, and Manage Project Team Acquire, develop and assign resources as per the project plan Acquire, develop and assign resources as per the project plan Acquire, develop and assign resources as per the project plan
Distribute Info, Manage Stakeholder Expectations and Report Performance Ensure the resources know what to do when, and have the requirements for each task Ensure the resources know what to do when, and have the requirements for each task Ensure the resources know what to do when, and have the requirements for each task
Control Costs Manage costs as per the project plan Manage costs as per the project plan Manage costs as per the project plan
Verify and Control Scope Manage the scope against the project plan Manage the scope against the project plan Manage the scope against the project plan
Control Schedule Ensure project tracks schedule to meet overall goals Ensure project tracks schedule to meet overall goals Ensure project tracks schedule to meet overall goals
Monitor and Control Risks Continually manage the project risks Continually manage the project risks Continually manage the project risks
Conduct and Administer Procurements Execute on procurement plan Execute on procurement plan (i.e. all purchases and contract manufacturer setup)
Perform Integrated Change Control Make changes to the project plan as appropriate and approved Make changes to the project plan as appropriate and approved Make changes to the project plan as appropriate and approved
Engineering is to perform the work according to the project plan. Using the schedule, likely some rolling wave planning, good requirements and WBS, the engineers will design and deliver an Alpha build and early Beta builds. Earned value management is a great tool to track and report project performance during Execution. The manufacturing and Manufacturing Engineering teams will work closely with Engineering. Ensure an excellent system of communication is in place starting at the planning stages to ensure a smooth product release.

 PMI –Closing

PDLC – Project Close-out

Close Project or Phase Perform a lessons learned review Perform a lessons learned review Perform a lessons learned review